Anyone know why the road works at the intersection of Pialligo Ave and Scherger Dr have come to a halt?

No machinery on site and no progress for weeks.


What's Your Opinion?


Please login to post your comments, or connect with
2 Responses to Ask RiotACT: Road works missing in action
Filter
Order
Whitepointer Whitepointer 7:33 pm 06 Aug 17

Apparently waiting for a water main connection to be done by the local water authority that wasn’t allowed for in the design by the consultants. Very common problem in Canberra…incompetent consultants.

gazket gazket 9:15 pm 07 Aug 17

I only mentioned it 3 or 4 months ago to Mark Parton they only have foot path machinery finishing off a dual carriage way road. There was a bobcat, 2 mini excavators and a mini off road dump truck smaller than a ute and no earth moving machinery at all on site .

Typical we have the government dragging their feet to connect a pipe . Probably waiting for the 457 contractor to get their visas .

CBR Tweets

Sign up to our newsletter

Top
Copyright © 2020 Region Group Pty Ltd. All rights reserved.
the-riotact.com | riotact.com.cn | aboutregional.com.au | b2bmagazine.com.au | thisiscanberra.com

Search across the site